Title: ACCEPTANCE OF THE CITYWIDE PARKWAY MAINTENANCE, STREET REHABILITATION, AND SLURRY SEAL PROJECT, CITY PROJECT NO. 21-03
Attachments: 1. Agenda Report, 2. 1. Location Map, 3. 2. Final Contract Cost Summary
Related files: 21-519
TITLE:
title
ACCEPTANCE OF THE CITYWIDE PARKWAY MAINTENANCE, STREET REHABILITATION, AND SLURRY SEAL PROJECT, CITY PROJECT NO. 21-03
end
DEPARTMENT: PUBLIC WORKS DEPARTMENT/ENGINEERING DIVISION
PRESENTED BY: RAJA SETHURAMAN, PUBLIC WORKS DIRECTOR
CONTACT INFORMATION: SEUNG YANG, P.E., CITY ENGINEER, (714) 754-5633

RECOMMENDATION:
recommendation
Staff recommends the City Council:
1. Accept the work performed by All American Asphalt, Inc., 400 East Sixth Street, Corona, California 92879 for the Citywide Parkway Maintenance, Street Rehabilitation, and Slurry Seal Project, City Project No. 21-03, and authorize the City Clerk to file the Notice of Completion.

2. Authorize the City Manager to release the retention monies thirty-five (35) days after the Notice of Completion filing date; release the Labor and Material Bond seven (7) months after the filing date; and release the Faithful Performance Bond one (1) year after the filing date.
end
BACKGROUND:
On February 1, 2022, the City Council awarded a construction contract to All American Asphalt, Inc. for the Citywide Parkway Maintenance, Street Rehabilitation, and Slurry Seal Project, City Project No. 21-03.

The City conducts an annual capital improvement program repairing, improving, and installing new concrete parkways and asphalt road surfacing. The scope of work for the Citywide Parkway Maintenance, Street Rehabilitation, and Slurry Seal Project ("Project") consists of concrete parkway repair, general asphalt concrete (AC) rehabilitation, slurry sealing of streets, and any additional work needed to complete the Project in accordance with the project specifications.

Staff combined the tasks of parkway maintenance, street rehabilitation, and slurry seal into one construction project in order to achieve economies of scale and cost savings, which will result in reduced mobilization costs, lower unit prices for material, equipment, and labor.
The street rehabilitation improvements are citywide, but the pr...