City of Costa Mesa Banner
File #: 22-886    Version: 1
Type: Report Status: Agenda Ready
File created: 9/27/2022 In control: REGULAR CITY COUNCIL AND HOUSING AUTHORITY*
On agenda: 10/18/2022 Final action:
Title: ACCEPTANCE OF THE FIRE STATION NO. 3 IMPROVEMENTS AND REPAIRS PROJECT, CITY PROJECT NO. 21-06
Attachments: 1. Agenda Report, 2. 1. Final Costs
Related files: 21-386
TITLE:
title
ACCEPTANCE OF THE FIRE STATION NO. 3 IMPROVEMENTS AND REPAIRS PROJECT, CITY PROJECT NO. 21-06

end
DEPARTMENT: PUBLIC WORKS DEPARTMENT/ENGINEERING DIVISION
PRESENTED BY: RAJA SETHURAMAN, PUBLIC WORKS DIRECTOR
CONTACT INFORMATION: SEUNG YANG, P.E., CITY ENGINEER, (714) 754-5633
RECOMMENDATION:
recommendation
Staff recommends the City Council:

1. Accept the work performed by Urban Professional Builders, Inc., 157 El Nido Avenue, Pasadena, CA 91107, for the Fire Station No. 3 Improvements and Repairs Project, City Project No. 21-06, and authorize the City Clerk to file the Notice of Completion.

2. Authorize the City Manager to release the retention monies thirty-five (35) days after the Notice of Completion filing date; release the Labor and Material Bond seven (7) months after the filing date; and release the Faithful Performance Bond, if appropriate, at the conclusion of the one-year warranty period.
end
BACKGROUND:
Fire Station No. 3, located in District 5 at 1865 Park Avenue, provides fire protection and emergency response services to the Costa Mesa community. The Fire Department's mission is to prevent the loss of life and property. In addition to combating fires, emergency responders at Fire Station No. 3 also tend to medical emergencies, motor vehicle accidents, rescue calls, and incidents involving hazardous materials.

For several years, Fire Station No. 3 has undergone maintenance issues and required repairs. Issues that needed to be addressed included preventing water seepage through the exterior walls, grading of the soil away from the fire station, relocating existing drainage pipes, performing concrete repairs, reconstructing new front driveway, conducting roof repair including drain spouts, and landscaping.

On October 5, 2021, a construction contract in the amount of $274,000 was awarded to Urban Professional Builders, Inc.



ANALYSIS:
The work required by the contract documents was completed on September 23, 2022 to the s...