Legislation Details

File #: 26-456    Version: 1
Type: Report Status: Agenda Ready
File created: 10/8/2026 In control: REGULAR CITY COUNCIL AND HOUSING AUTHORITY*
On agenda: 10/29/2026 Final action:
Title: FACILITIES MASTER PLAN FOR CITY OWNED FACILITIES PRESENTATION
Attachments: 1. Agenda Report, 2. 1. Facilities Master Plan Report
Related files: 26-161
TITLE:
title
FACILITIES MASTER PLAN FOR CITY OWNED FACILITIES PRESENTATION
end
DEPARTMENT: PUBLIC WORKS DEPARTMENT/GENERAL SERVICES DIVISION
PRESENTED BY: RAJA SETHURAMAN, PUBLIC WORKS DIRECTOR
CONTACT INFORMATION: PATRICK BAUER, DEPUTY PUBLIC WORKS DIRECTOR, (714) 754-5029

RECOMMENDATION:
recommendation
Staff recommends the City Council receive and file this Facilities Master Plan report.
end
BACKGROUND:
On January 21, 2025, the City Council approved a Professional Services Agreement (PSA) with Gensler for the preparation of a Facilities Master Plan. The purpose of the project was to evaluate the conditions of various City facilities and assess their current and future usage and needs. The project also included meetings with various departments to understand and incorporate their feedback on various facilities. The City facilities that were assessed included Balearic Community Center, Bridge Shelter, City Hall, Communications Building, Corporation Yard Buildings A and B, Downtown Recreation Center, Fire Station Nos. 1, 3, 4, 5, and 6, Historical Society Building, Mesa Verde Library, Police Facility, Police Westside Substation, and Senior Center. In order to accomplish this, the project was structured into three phases:

Phase 1: Facility Condition Assessment

This phase involved a comprehensive evaluation of each facility. Inspections focused on observable areas and systems, supplemented by input from City staff regarding facility conditions and historical background.

Phase 2: Space Needs Assessment and Gap Analysis

This phase analyzed current operations, services, and programs of identified facilities to determine their utilization. Surveys were conducted to identify present and future space requirements for current and future staffing needs for each facility.



Phase 3: Cost Estimates and Funding Strategies

In this final phase, cost estimates and potential funding strategies were developed for the recommended improvements, proposed implementat...

Click here for full text