AWARD OF THE NORMA HERTZOG COMMUNITY CENTER ROOF REPLACEMENT PROJECT, CITY PROJECT NO. 25-05
end
DEPARTMENT: PUBLIC WORKS DEPARTMENT/GENERAL SERVICES DIVISION
PRESENTED BY: RAJA SETHURAMAN, PUBLIC WORKS DIRECTOR
CONTACT INFORMATION: PATRICK BAUER, DEPUTY PUBLIC WORKS DIRECTOR (714) 754-5029
RECOMMENDATION:
recommendation
Staff recommends the City Council:
1. Award a Public Works Agreement (PWA) in the amount of $745,276 to C.I. Services, Inc. 1145 E. Stanford Court, Anaheim, CA, 92805 to remove and replace metal roofing panels.
2. Authorize a ten percent (10%) contingency in the amount of $74,528 for unforeseen costs related to the project.
3. Authorize the Interim City Manager and City Clerk to execute the PWA and any future amendments to the agreement.
4. Authorize a budget transfer of $191,206 in City Capital Improvement Program funds from the Lions Park Caf? Project (#800032) to the Norma Hertzog Community Center Roof Replacement Project (#210025).
end
BACKGROUND:
The Norma Hertzog Community Center (NHCC), located at 1845 Park Avenue, Costa Mesa, CA, 92627 is the City's newest rental facility. It features a large meeting room complete with a stage and integrated AV system suitable for events, receptions, large meetings, and classes. It also includes a smaller meeting room along with an outdoor patio area. During the prior renovation of NHCC, the old metal roof was not replaced. The roof has since experienced leaks during periods of heavy rainfall.
The proposed work for this project will assist in keeping the facility safe from rainwater leaks, causing damage to the walls, AV system, the roof itself, and other components of the building. The proposed work consists of removing the existing roofing, prepping the area for replacement, and installing new modified bituminous roofing and manufactured metal roofing panels per the Garland Company's shop drawings and the project specification.
ANALYSIS:
On February 27, 2025, the City rece...