TITLE:
title
FINAL PARCEL MAP NO. 2023-160 LOCATED AT 695 WEST 19TH STREET, COSTA MESA, CALIFORNIA AND ACCESS, PARKING AND DRAINAGE EASEMENTS AGREEMENT
end
DEPARTMENT: PUBLIC WORKS DEPARTMENT/ENGINEERING DIVISION
PRESENTED BY: RAJA SETHURAMAN, PUBLIC WORKS DIRECTOR
CONTACT INFORMATION: SEUNG YANG, P.E., CITY ENGINEER (714) 754-5335
RECOMMENDATION:
recommendation
Staff recommends the City Council:
Approve final Parcel Map No. 2023-160, located at 695 West 19th Street and authorize signing of the map by the Mayor and the City Clerk.
Approve the Access, Parking and Drainage Easements Agreement, which is referenced on the final Parcel Map, and will be recorded immediately following the Parcel Map to reserve required easements over the newly separated parcel for access, parking and drainage for the benefit of the public and the remaining parcel which the Senior Center occupies, as well as preserving the priority of these easements over any other liens or other encumbrances on the newly formed parcel.
end
BACKGROUND:
On March 18, 2025, a Master Plan (PMAP-24-0001) with Density Bonus to construct a 70-unit senior affordable multi-family residential project at 695 West 19th Street was approved by the City Council, also known as the Jamboree Housing Project. At that time, the City Council also approved Tentative Parcel Map 2023-160, which consists of subdividing the 2.66-acre property occupied by the Costa Mesa Senior Center and parking lot into two lots and the Conditions of Approval included in Resolution No. 2025-04. (Attachment 1). The original Tentative Map made reference to a future easement to be recorded against the new parcel, and the parties have now reached agreement on the language of that final easement agreement. (Attachment 3).
ANALYSIS:
This subdivision map will subdivide a portion of Lot 501, (created per map recorded in Book 5, Page 1 of the Official Records, in the Office of the Orange County ClerkâRecorder, State of California). The f...