Title: AWARD OF THE INFORMATION TECHNOLOGY DEPARTMENT REMODELING PROJECT, CITY PROJECT NO. 22-09
Attachments: 1. Agenda Report, 2. 1. Bid Abstract, 3. 2. Project Cost Summary
Related files: 24-273
TITLE:
title
AWARD OF THE INFORMATION TECHNOLOGY DEPARTMENT REMODELING PROJECT, CITY PROJECT NO. 22-09
end
DEPARTMENT: PUBLIC WORKS DEPARTMENT/ENGINEERING DIVISION
PRESENTED BY: SEUNG YANG, P.E., CITY ENGINEER
CONTACT INFORMATION: SEUNG YANG, P.E., CITY ENGINEER, (714) 754-5633

RECOMMENDATION:
recommendation
Staff recommends the City Council:

1. Adopt plans, specifications, and working details for the Information Technology Department Remodeling Project, City Project No. 22-09.

2. Authorize the City Manager and City Clerk to execute a Public Works Agreement (PWA) for construction to Builtall, 4712 East 2nd Street, #520, Long Beach, California 90803 in the amount of $255,020, plus a ten percent (10%) contingency for the PWA and also contracts referenced below for a total contingency of $42,279, and authorize a budget appropriation from available fund balances in the amount of $250,000.

3. Authorize the City Manager or designee to execute the agreements and any future amendments to the agreements including increases to the not-to-exceed amount within City Council authority.

ENVIRONMENTAL DETERMINATION:

The proposed action is exempt from the California Environmental Quality Act (CEQA). The action involves an organizational or administrative activity of government that will not result in the direct or indirect physical change in the environment. In addition, the proposed action is exempt under Section 15301 relating to the operation, repair, maintenance, permitting, and/or minor alteration of existing public facilities.

end
BACKGROUND:
The Information Technology (IT) Department Remodeling Project was approved during Fiscal Year 2016-17. Staffing at that time comprised eleven (11) full-time positions, one (1) management, two (2) supervisory, seven (7) professional, and one (1) clerical position. Due to staffing shortages and the onset of the COVID-19 pandemic, the project was temporarily deferred.

Current staffing in the IT Department now consists...