Skip to main content
City of Costa Mesa Banner
File #: 23-1345    Version: 1
Type: Report Status: Agenda Ready
File created: 8/3/2023 In control: PARKS AND COMMUNITY SERVICES COMMISSION
On agenda: 8/10/2023 Final action:
Title: KETCHUM-LIBOLT PARK AND SHALIMAR PARK PROJECTS UPDATE
Attachments: 1. Agenda Report, 2. 1. Costa Mesa Summary for Parks Projects
TITLE:
title
KETCHUM-LIBOLT PARK AND SHALIMAR PARK PROJECTS UPDATE
end
DEPARTMENT: PUBLIC WORKS DEPARTMENT
PRESENTED BY: RAJA SETHURAMAN, PUBLIC WORKS DIRECTOR
CONTACT INFORMATION: RAJA SETHURAMAN, PUBLIC WORKS DIRECTOR, (714) 754-5343

RECOMMENDATION:
recommendation
Provide an update and seek input on Ketchum-Libolt Park and Shalimar Park improvements.
end
BACKGROUND:
As part of the current Fiscal Year 2023-24 Capital Improvement Program (CIP) budget, the City Council appropriated grant funds received through Assemblymember Cottie Petrie Norris' office and Senator Min's office for Ketchum-Libolt Park and Shalimar Park, respectively. An appropriation of $1.2 million for upgrades to Ketchum-Libolt Park was secured by the Assemblymember for park expansion and recreation amenities. An appropriation of $1 million for park expansion and rehabilitation of Shalimar Park was approved by City Council from the $10 million state grant received through State Senator Min.
ANALYSIS:
In order to understand community needs prior to proceeding with the formal design process, the City engaged the services of Pat West, LLC, for community outreach and engagement, and City Fabrik, for the preparation of conceptual rendering of ideas generated by the community. A total of six (6) community engagement meetings were held in May and June at Ketchum-Libolt and at Shalimar Parks to solicit input. Attachment 1 provides a summary of the community engagement activities.
City Fabrik attended several of the community outreach meetings and interacted with several community members. Using the feedback received from stakeholders as well as staff, conceptual renderings were prepared by City Fabrik. These conceptual renderings will be presented during this Parks and Community Services Commission Meeting for further discussion and input. Staff will use these renderings for soliciting consultants for final design.
Over the next three months, staff will be soliciting design proposals a...

Click here for full text