Title: ACCEPTANCE OF THE NORMA HERTZOG COMMUNITY CENTER ROOF REPLACEMENT PROJECT, CITY PROJECT NO. 25-05
Attachments: 1. Agenda Report, 2. 1. Final Cost
Related files: 25-435
TITLE:
title
ACCEPTANCE OF THE NORMA HERTZOG COMMUNITY CENTER ROOF REPLACEMENT PROJECT, CITY PROJECT NO. 25-05
end
DEPARTMENT: PUBLIC WORKS DEPARTMENT/GENERAL SERVICES DIVISION
PRESENTED BY: RAJA SETHURAMAN, PUBLIC WORKS DIRECTOR
CONTACT INFORMATION: PATRICK BAUER, DEPUTY PUBLIC WORKS DIRECTOR, (714) 754-5029

RECOMMENDATION:
recommendation
Staff recommends the City Council:

Accept the work performed by C.I. Services, Inc. for the Norma Hertzog Community Center Roof Replacement Project, City Project No. 25-05, and authorize the City Clerk to file the Notice of Completion.

Authorize the City Manager to release the retention monies thirty-five (35) days after the Notice of Completion filing date; release the Labor and Material Bond seven (7) months after the filing date; and release the Faithful Performance Bond one (1) year after the filing date.

end
BACKGROUND:
On September 16, 2025, City Council awarded a construction contract for $745,276 to C.I. Services, Inc. for the Norma Hertzog Community Center Roof Replacement Project, City Project 25-05.
The scope of work for this project consisted of removing the existing metal roofing panels, metal wall panels, metal gutters, and flat roofing; prepping the underlying roof; and replacing it with all new metal roofing and wall panels, metal capping and flashing, and flat bituminous roofing. All metal replaced is of the same color to provide a cleaner and more consistent aesthetic appeal. The contractor has also provided all necessary warranty documentation.

ANALYSIS:
The contractor, C.I. Services, completed the roof tear off, preparation, installation, and final cleaning in an efficient and timely manner. No change orders were issued.

The work required by the project was completed on June 25, 2026, to the satisfaction of the Deputy Public Works Director and the City Engineer, with a final contract cost of $703,276. The final Public Works inspection and Building Department inspection passed with no issues...