City of Costa Mesa Banner
File #: 24-137    Version: 1
Type: Report Status: Agenda Ready
File created: 4/18/2024 In control: REGULAR CITY COUNCIL AND HOUSING AUTHORITY*
On agenda: 5/7/2024 Final action:
Title: ACCEPTANCE OF THE CITY HALL ELEVATORS MODERNIZATION, CITY PROJECT NO. 20-03
Attachments: 1. Agenda Report, 2. 1. Final Costs
TITLE:
title
ACCEPTANCE OF THE CITY HALL ELEVATORS MODERNIZATION, CITY PROJECT NO. 20-03
end
DEPARTMENT: PUBLIC WORKS DEPARTMENT/ENGINEERING DIVISION
PRESENTED BY: RAJA SETHURAMAN, PUBLIC WORKS DIRECTOR
CONTACT INFORMATION: SEUNG YANG, P.E., CITY ENGINEER (714) 754-5335

RECOMMENDATION:
recommendation
Staff recommends the City Council:
1. Accept the work performed by GMS Elevator Services, Inc., 401 Borrego Court, San Dimas, CA 91773, for the City Hall Elevators Modernization, City Project No. 20-03, and authorize the City Clerk to file the Notice of Completion.

2. Authorize the City Manager to release the Labor and Material Bond seven (7) months after the filing date and release the Faithful Performance Bond at the conclusion of the one-year warranty period. Retention monies have been released pursuant to Public Contract Code 7107(c).

end
BACKGROUND:
On July 21, 2020, a construction contract in the amount of $662,000 was awarded to GMS Elevator Services, Inc. for the City Hall Elevators Modernization Project.

The elevators were originally built and installed in the late 1960s with upgrades to the control microprocessor systems completed in 1995. The gear boxes were no longer manufactured or supported, which made the purchase of maintenance parts difficult.

The project scope of work included new motor drive units, electrical controllers, hoist way systems, communications controllers, safeties, roller guides, cab doors, door operators, interior control panels, indicators, and wiring. The project also included aesthetic upgrades to the cab interior walls, ceiling, floor, push buttons, lights, and panels.

The construction is now complete and is ready to be accepted by the City Council.

ANALYSIS:
The work required by the contract documents was completed to the satisfaction of the City Engineer. The final contract cost amounted to $594,000. A report of the final costs is included as Attachment 1.

A summary of the costs is as follows:

Initial Contrac...